February 20th - Progress Update

We’re getting closer and closer! The Bathrooms, Cafe, Front Desk, the majority of the electrical work and all of the HVAC work is nearly complete. As of now we’re just waiting on the climbing walls, which should be arriving in the next few weeks. Here’s a quick (hopeful) timeline of the home stretch:

March 2: Climbing Walls Arrive

March 2 - 21: Climbing Walls Installed

March 21 - April 1: Flooring Installed

First Week of April: Final Touches

…then we wait for the city to sign off and issue us our Certificate of Occupancy.

We are currently projecting a mid-April opening but as all things go with large construction projects, delays can and will happen.

Here’s a quick glimpse of what the space looks like so far:

Stay tuned to see it come to life over the next few weeks.